Machinery Planning: Schedule Maintenance Between Sites

A machine that finishes a project may seem available for the next one, even though a visit to the workshop is already scheduled. If you confirm its arrival without considering this stop, the team might end up waiting on-site and the schedule will need to be revised.

Before setting the next date, you must account for the entire period of unavailability, from departure for maintenance to the expected return. This period should be part of the same schedule as the work to which the machine is assigned.

Try the planner

A day without a project may already be occupied

The appointment may have been arranged with the workshop without being reported in the project schedule. When preparing for the next departure, the day appears free even though the machine needs to be immobilized.

Forgetting the stop also affects the team and transport

A team already scheduled to use the machine must reconsider what can be advanced while waiting. You need to call the concerned individuals, change the departure date, or find a replacement machine if the work needs to start as planned.

The transport reserved for the next project may also need to be rescheduled. The correction thus affects the machine's dates, the employees' dates, and the instructions already given to the person responsible for the transport.

ConstruMD shows the stop with the scheduled projects

The ConstruMD resource planner groups projects under each machine and allows you to enter its downtime in the same calendar. The visit to the workshop becomes visible when you review its next use.

In our planner, the stop is manually entered on the machine's Vacation line, in the Resources view. You specify the start date, the duration in working days, and the hours of downtime per day. A note allows you to keep what needs to be confirmed with the workshop before the next project.

Downtime day for Mini-excavator ME-01 on December 17 with eight hours of unavailability and a note on workshop maintenance

Demonstration data. The downtime on December 17 covers the eight hours of the day scheduled for this machine. The note specifies the visit to the workshop and the return to be confirmed before the next project.

The ConstruMD planner then displays the period under the label “Out of Service”. The hatching on the project lines indicates the affected days when you check the machine's assignments.

The visit to the workshop fits between the two projects

In this demonstration, the Mini-excavator ME-01 is scheduled at the CHSLD des Rives from December 14 to 16. The downtime on the 17th covers eight hours, then its use at Nordspa is scheduled for the 18th. The note asks to confirm its return before the next project.

ConstruMD calendar of Mini-excavator ME-01 with CHSLD des Rives from December 14 to 16, a stop on the 17th, and Nordspa on the 18th

Demonstration data. The turquoise period for CHSLD des Rives is scheduled from December 14 to 16. The 17th is reserved for the stop, with visible hatching on the project lines. The orange period for Nordspa is scheduled for the 18th.

To prepare for the departure to Nordspa, you can see until when the machine is scheduled at CHSLD des Rives and the day reserved for the workshop. These two periods help you choose the date for the next project.

Schedule the team and transport at the right time

Before confirming this date, agree with the workshop on the machine's return and organize its transport. If the expected return does not allow for the planned schedule, you can arrange for another machine or revise the start of the work.

When multiple projects need the same machine, also check its other reservations. The chosen date is then used to prepare the team schedule, with the employees who will use the machine when its arrival is expected.

You can then communicate to the employees a date that takes into account the expected return of the machine and its transport.

Try the ConstruMD planner for free for seven days and integrate the next machine stop into your project preparations.