The price of diesel has once again become a major operational risk for construction companies in Quebec. In Quebec City, reported prices reached $2.955 per litre on September 17, 2026. At this level, the cost is no longer limited to filling up the truck: it extends to excavators, loaders, generators, deliveries, subcontractors, material transport, and travel between sites.
The danger is primarily contractual. A company may have bid with a much lower reference price and then have to perform the work several weeks later. If the contract is fixed-price and contains no adjustment mechanism, the increase may be absorbed directly by the margin.
Here is a simple and verifiable method to understand the increase, calculate its real impact, and decide what to do in bids and contracts.
First, it is important to distinguish between three types of figures. The price displayed today at a station is a local and one-time price. A monthly average summarizes a period that has already passed. A contractual reference price finally serves as the basis for a determined formula.
For certain bulk trucking rates, the Ministry of Transport and Sustainable Mobility publishes a fuel average price of $2.188 per litre for September 2026. This data corresponds to the previous month's average price used in the applicable adjustment mechanism. It does not mean that all stations were selling diesel at this price on September 17.
On the same day, daily price declarations for the city of Quebec showed a peak of 2.955 $ per litre. The gap illustrates why a contractor must date and locate their data rather than using an isolated figure.
Since April 1, 2026, merchants targeted by section 67.1 of the Petroleum Products Act must make their prices accessible on a Régie platform. In practice, this means that Régie essence Québec allows verification of the declared price at stations in a region before updating a bid or planning a refueling.
The pump price depends not only on the price of crude oil. It also depends on refining capacity, available diesel supply, demand, transportation, exchange rate, margins, and applicable taxes.
The federal government attributes part of the current surge to conflicts in Europe and the Middle East. It announced on September 15, 2026, the extension of the suspension of the federal excise tax on diesel until January 31, 2027. For diesel, this relief represents 4 cents per litre.
This measure reduces the bill compared to what it would be with the full tax, but it does not neutralize an increase of several tens of cents. In other words, the price can remain very high even if a 4-cent tax is temporarily suspended.
The calculation must start from the company's data. A universal consumption rate would be misleading, as an excavator, a loader, a generator, and a truck do not consume the same amount. The condition of the equipment, the load, idling, terrain, temperature, and working method also affect consumption.
Fuel cost = litres consumed per hour × planned hours × price per litre.
The number of litres per hour should come from refueling records, telematics, or, failing that, manufacturer data adjusted to actual use. An average calculated over several weeks is generally more reliable than a single day.
Fuel cost = consumption in L/100 km × planned kilometres ÷ 100 × price per litre.
It is necessary to include trips that truly belong to the project: mobilization, deliveries, round trips to the quarry or supplier, travel between two sites, and empty returns when they are part of the operation.
Additional cost = planned litres × difference between the current price and the reference price.
Purely mathematical example: if diesel increases by $0.75 per litre and the site consumes 1,000 litres, the direct increase is $750. At 10,000 litres, it becomes $7,500. The calculation is not an automatic surcharge to the client; it is primarily used to measure risk.
A contractor can reduce some trips, but they do not control the entire chain. A supplier may increase their delivery fees. A carrier may apply a mechanism provided in their contract. A subcontractor may revise their new prices. A quarry, equipment rental company, or container service may also pass on part of their costs.
It is therefore necessary to separate the fuel consumed directly by the company from the indirect costs already integrated into supplier prices. Adding the two without verification risks counting the same increase twice.
Labour remains another distinct component. As explained in our guide on the total cost of a CCQ payroll, the gross salary alone does not represent the employer's actual expense. To know the margin of a project, fuel, labour, materials, equipment, and overhead must remain in separate categories.
No, not automatically. The right to adjust the price depends on the contract, the accepted bid, applicable clauses, and the context. A general increase in diesel prices does not by itself transform a fixed price into a variable price.
Before claiming a supplement, it is necessary to check if the contract includes a fuel adjustment clause, an indexation clause, an allowance, a formula linked to an index, or a change mechanism. It is also important to verify the reference price, the start date, the trigger threshold, supporting documents, limits, and how the adjustment should be approved.
Public contracts or regulated rates may have their own mechanisms. For example, the MTQ publishes adjustment rates for certain bulk trucking rates and offers a fuel surcharge calculation tool. This method does not automatically apply to all private construction contracts; it rather shows what a documented mechanism looks like.
A useful clause should clearly identify the targeted fuel, the price source used, the region, the reference date or period, the formula, the minimum variation threshold, the update frequency, and how to handle a decrease.
A balanced clause does not only work when the price goes up. If it transfers an increase to the client, it should also explain what happens when the price goes down. This symmetry makes the formula more credible and reduces conflicts.
For new contracts, it is wise to have important clauses validated by a qualified person. For an already signed contract, it is important to avoid inventing a surcharge after the fact without a contractual basis or written agreement.
The bid can indicate the diesel price used in the calculation, its source, its region, and its date. The client can then see on what assumption the amount is based.
A bid valid for a long period exposes the company more to variation. A clear validity period prevents a price prepared in a different market from being accepted several months later without revision.
Highly mechanized, remote, or transport-rich projects deserve a separate calculation line. The more consumption is hidden in a global amount, the harder it becomes to explain a discrepancy or verify a margin.
A uniform supplement of 5% or 10% may be too high for a light project and insufficient for an earthmoving site. A formula linked to litres, hours, or kilometres better reflects the actual exposure.
Even a correctly calculated margin can be weakened if the company finances the fuel for several weeks before being paid. For the targeted public contracts, our article on the rapid payment regime in construction explains the new rules that further regulate the payment chain.
The first measure is to track litres by equipment and by project. Without this information, the company knows how much it pays in total, but not which project consumes the margin.
The second is to reduce unnecessary idling, incomplete trips, and avoidable detours. It is not about rushing workers or bypassing safety rules, but about better planning logistics, deliveries, and refuelling.
The third is to compare local prices on the official platform before a significant fill-up. A few cents difference becomes significant when a mobile tank or several pieces of equipment are refuelled.
The fourth is to quickly talk to clients and subcontractors. A discussion based on a formula, invoices, and a public source is more solid than a vague request explaining that "everything costs more."
A week of extreme prices is not enough to decide to sell a profitable truck or excavator. The decision should compare the total cost of ownership, annual usage, financing, maintenance, resale value, availability of a replacement solution, and planned contracts.
Renting, subcontracting, or electric equipment may be relevant in some cases, but no choice is universal. Equipment that is rarely used may be too expensive to keep, while essential and productive machinery may remain profitable despite more expensive fuel.
Diesel near $3 per litre is a real risk for Quebec construction, but the impact is not measured by an impression. It is calculated with litres, hours, kilometres, the reference price, and contract clauses.
To protect the margin, a company must date its assumptions, track consumption by project, separate direct costs from costs passed on by suppliers, and use a clear formula in new bids.
The fuel price will eventually change. The management method, however, should remain: real data, clear contract, preserved proof, and quick communication.