First aider on a construction site in Quebec: how many are needed and who pays?

The general rule is simple: as soon as 10 workers are simultaneously assigned to a construction site, the project manager must ensure the presence of at least one first responder during each work shift. The number then increases with the workforce present.

This obligation is not just about having someone who has previously taken a first aid course. The first responder must hold a valid certificate recognized by the CNESST, be able to intervene quickly, and be identifiable on the site. The site must also have accessible kits, a means of communication with emergency services, and a record of interventions.

Here are the concrete rules to apply, the responsibilities of each party, and the mistakes that most often create confusion.

First responder checking a first aid kit with a team on a construction site in Quebec

The short answer: the required number of first responders

Article 7 of the Regulation on Minimum Standards of First Aid and First Aid sets the minimum number of first responders on a construction site. The calculation is based on the number of workers simultaneously assigned to the site during a work shift.

Fewer than 10 workers

The general regulation on first aid does not require the presence of a first responder on a site where fewer than 10 workers are simultaneously assigned. This does not eliminate other health and safety obligations. A specialized task, a rescue procedure, or a particular risk may require additional measures.

From 10 to 50 workers

At least one first responder per work shift is required.

From 51 to 150 workers

At least two first responders per work shift are required.

Starting from 151 workers

Add one first responder for each additional hundred or fraction of a hundred workers. A site with 151 workers therefore needs three first responders. It also needs three for 225 workers, then four for 251 workers.

Table of the minimum number of first responders based on the number of workers present on a site

Count the people present, not the size of each company

The threshold applies to the site and the work shift. It is not calculated separately for each specialized contractor. An electrician, a carpenter, a labourer, and a subcontractor's worker count in the workforce when they are simultaneously assigned to the site.

The practical question is: how many workers will be present at the same time during the shift? A site with eight workers in the morning and twelve in the afternoon crosses the threshold when the twelve people are present. The first aid plan must follow the reality of the schedule, teams, and work phases.

Changes in workforce must be anticipated. The arrival of a new subcontractor, an evening shift, or a peak period can move the site into a higher category without the emergency organization being adjusted.

Who is responsible: the project manager

On a site, the regulatory responsibility to ensure the presence of the required number of first responders belongs to the project manager. The regulation defines the project manager as the owner or the person who assumes responsibility for the execution of all the work.

This responsibility does not prevent contractors and subcontractors from collaborating. A worker from a specialized contractor can be designated as a first responder if they hold a valid certificate, are actually present during the shift, and their work allows them to intervene quickly. The project manager must, however, ensure that coverage remains sufficient for the entire site.

Absences must also be planned for. A first responder who is out for delivery, on a break outside, assigned to an inaccessible area, or constantly moved between multiple sites does not effectively cover the site. The CNESST specifies that the nature of their work must not compromise the speed and effectiveness of their intervention.

What training is recognized?

To become a workplace first responder, the worker must take training in accordance with the regulation from an organization recognized by the CNESST. The first responder training lasts 16 hours and includes an evaluation.

The certificate is valid for three years. To renew it, the worker must retake the training. An expired old card is not sufficient, even if the person has a lot of experience.

The General Health and Safety on Construction Sites course, often called the ASP Construction card, does not replace the first responder certificate. The ASP card is a general requirement for site access; first aid training is a distinct qualification.

Is another first aid course sufficient?

Not automatically. A CPR or first aid course taken for a personal activity can be useful, but it does not necessarily prove that the person holds the certificate required by the regulation. The project manager must verify the validity of the certificate and the recognition of the training organization.

Who pays for the training and the worker's time?

The person designated to become a first responder can be absent from work without loss of salary for the time necessary to obtain or renew their certificate. The CNESST also reminds that the first responder is considered to be at work and must be paid when they take the required training and when they intervene during their working hours.

For construction, the CNESST can subsidize training corresponding to 10% of the number of workers. The subsidy is paid directly to the recognized training organization, and the calculation takes into account the training already funded during the three-year validity period.

The general contractor assumes the costs related to the implementation and maintenance of first aid services on the site. The regulation also assigns them the necessary travel expenses of the designated person when the training or refresher can be offered within 40 km of the site where they work.

If the number of trained individuals exceeds the number covered by the subsidy, additional training may be billed according to the agreement with the organization. Therefore, subsidized training should not be confused with the absence of any cost for the organization.

How to recognize the first aider on the site?

The regulation requires that the first aider(s) on a site be identified by wearing a safety helmet marked with a cross. The goal is to allow workers to quickly find the right person when an incident occurs.

The identification must remain visible and understood by the teams. The names of the first aiders, their usual area, and how to contact them can also be mentioned during the welcome, at the start of the shift, and in the minutes of a safety meeting. A list that is not updated after a team change gives a false impression of compliance.

First aid kits

The general contractor must provide an adequate number of kits and make them available at all times. On a site covered by the regulation, the number is considered adequate when each worker can normally access a kit in about five minutes.

The minimum content of the kits must comply with the CSA Z1220 standard. The risk level of the environment and the number of workers per shift determine the type and quantity of materials. An over-the-counter kit may be suitable if its content meets the standard; no special certification of the container is required.

The kit must remain clean, complete, and in good condition. Used, soiled, damaged, or expired items must be replaced. Contrary to popular belief, it is not necessary to replace the entire kit every three years. It is the first aider's certificate that has this validity period.

Vehicles used far from a kit

A vehicle intended for the transport or use of workers must also have a kit when it operates in an area where no site kit is accessible within the prescribed time. The required content varies notably according to the vehicle's capacity and the distance from medical services.

The phone, signage, and register

The site must have an immediately accessible communication system to contact first aid services. The way to communicate with these services must be indicated near the system. Having a phone somewhere in a locked trailer does not meet the need if no one can access it quickly.

Calling 911 does not replace the required first aider. The first aider provides first aid while waiting for emergency services to arrive and conveys useful information about the situation.

After each intervention, the first aider must complete a report with their name, the name of the injured person, the date, time, description of the injury or ailment, and the nature of the aid given. The report is submitted to the general contractor and kept in the register. This register does not replace other notices and procedures required when there is a work-related injury.

Additional requirements on certain large sites

When more than 100 workers are present, the general contractor must set up an accessible room where the first aider can provide first aid. This room must be clean, ventilated, adequately lit and heated, and equipped with water, a stretcher, a table, chairs, and the materials required by the regulation.

Another rule applies to remote sites: when at least 25 workers are present simultaneously and it is impossible to reach emergency medical services within 30 minutes by land, the regulation imposes additional services, including a nurse and a first aid room according to the specified conditions.

These requirements do not replace the minimum number of first aiders. They are added when the size or remoteness of the site increases the risk associated with the medical intervention delay.

Special situations below the threshold of 10 workers

Saying that a site with fewer than 10 workers has no first aid obligations would be incorrect. It is not subject to the general obligation of Article 7, but the employer and the general contractor must always protect the health and safety of workers.

Certain tasks have their own rescue procedures or require a trained person to intervene. Working at heights with a planned rescue, confined spaces, and other specialized operations may therefore require a more demanding organization than the general minimum.

The right question is not only "are we fewer than 10?" but also "what risks are present and how will an injured person be rescued quickly?"

Five myths to leave behind

Myth 1: each subcontractor must provide their own first aider

The regulatory number is calculated for the site and is the responsibility of the general contractor. Contractors must collaborate, but the calculation is not repeated separately for each company.

Myth 2: the ASP card makes someone a first aider

No. A recognized workplace first aid certificate by the CNESST is required.

Myth 3: A first responder can cover multiple sites at the same time

No. The person must be present and able to intervene quickly on the site they are covering during the shift.

Myth 4: 911 replaces the presence of a first responder

No. The communication system and emergency services complement the first responder; they do not replace them.

Myth 5: The entire kit expires after three years

No. The three-year duration applies to the certificate. The kit should instead be checked, and its materials replaced based on their condition, usage, and expiration dates.

Simple Checklist Before the Start of the Shift

Workforce: Count the maximum number of workers present simultaneously, across all employers.

Coverage: Confirm the number of first responders required for each shift and each phase of the site.

Certificates: Check expiration dates and the recognized organization.

Availability: Ensure the first responder's duties allow for quick intervention and plan for a replacement in case of absence.

Identification: Check the cross on the helmet and inform the team.

Kits: Confirm they are accessible within about five minutes, complete, and suited to the risks.

Communication: Test the means to contact emergency services and post the instructions.

Register: Keep the intervention form available and know to whom it should be submitted.

This verification can be naturally integrated into daily planning. It becomes particularly important when risks change, for example during a period of heat on the site, an evening shift, or the arrival of a new team.

First aid verification checklist before a work shift on a construction site

Key Takeaways

On a construction site in Quebec, the general obligation begins with 10 workers present simultaneously. One first responder is required for 10 to 50 workers, two for 51 to 150, then one additional first responder per hundred or fraction of an additional hundred.

The main contractor must organize this coverage for each shift. The first responder must have completed the recognized 16-hour training, hold a valid three-year certificate, be able to intervene quickly, and wear a helmet marked with a cross.

Compliance also includes accessible kits, the communication system, signage, and the register. For a large, remote site or one exposed to particular risks, the minimum measures may not always suffice. Before starting work, the actual scenario should be validated with the CNESST or a health and safety professional when the situation falls outside the usual framework.