Building Code: Transition Extended Until 2027

Quebec has officially extended the transitional period for two important chapters of the Construction Code. For Chapter I, Building, and Chapter V, Electricity, certain previous provisions can still be used when work begins before October 17, 2027.

This decision does not remove the new codes or delay their implementation. Instead, it maintains, for an additional year, a window where the previous edition can still be used for an eligible project. This distinction is important for contractors, developers, professionals, and clients who must decide which edition to design, estimate, and execute a project.

Contractor and professional reviewing plans and a construction code on a site in Quebec

The Short Answer: Which Edition Can Be Used?

For Chapter I, Building, the provisions that existed before April 17, 2025, can be applied to the construction or transformation of a building if the work begins before October 17, 2027. The 2020 National Building Code modified Quebec has been in effect since April 17, 2025, and can be used now.

For Chapter V, Electricity, the provisions that existed before March 26, 2026, can be applied to the construction of an electrical installation if the work begins before October 17, 2027. The new Electricity chapter, based on the 2021 edition of the Canadian Electrical Code and Quebec modifications, also remains in effect.

The key word is begins. The date of the contract, bid, plans, or permit application does not automatically replace the actual start date of the work in question.

Timeline of the transition of the Building and Electricity chapters of the Construction Code until October 17, 2027

What Has Changed Since the Initial Announcement

The Building chapter based on the 2020 NBC modified Quebec came into effect on April 17, 2025. The initial regulation still allowed the use of previous provisions when work began before October 17, 2026.

The decree 1351-2026 published in the Quebec Official Gazette replaced the year 2026 with 2027 in this transitional provision. Published on August 26, 2026, the regulation came into effect on September 10, 2026. The extension is now official, not just announced or projected.

The Ordre des architectes du Québec summarizes the rule in the same way: the new deadline to start work according to the old standards is October 17, 2027, and it is the start of the work that determines the applicable edition.

This Is Not a Delay of the New Code's Implementation

Saying that the "new Code is delayed until 2027" is inaccurate. The new Building chapter has been in effect since April 2025. The new Electricity chapter has been in effect since March 2026. Designers and contractors can therefore prepare and carry out a project according to the new editions during the transition.

What is extended is the right to use the previous edition for work that begins before the new deadline. In other words, two regulatory paths remain possible during the transition, provided the project truly meets the criteria and the chosen edition is applied consistently.

Why This Distinction Changes a Bid

An edition of the Code can change dimensions, materials, calculations, equipment, accessibility details, safety measures, or electrical infrastructures. A bid prepared according to one edition, then executed according to another, can lead to revised plans, new purchases, method changes, and additional costs.

The extension provides time, but it does not eliminate the risk of transition. A project scheduled to start just before October 2027 may shift to the new rules if its timeline slips. This possibility should be addressed in design, estimation, tenders, and change clauses.

The Permit Date Alone Does Not Decide

A common belief is that a permit obtained before the deadline automatically "freezes" the old edition. The published transitional provision instead refers to work that has begun before October 17, 2027.

A project can have completed plans, confirmed financing, and a permit issued without the site having started. If the actual start of work occurs after the deadline, one should not assume that the old edition remains available. The responsible professional and the competent authority should confirm the applicable edition before mobilization.

What Exactly Does "Start of Work" Mean?

The regulation uses this expression without turning every preparatory action into an automatic start. A fence installed, a trailer delivered, a survey, or limited excavation should not be treated as universal proof without analyzing the project and the work in question.

To avoid a fragile decision, keep clear evidence of the actual start: daily reports, dated photos, invoices, delivery slips, mobilization contract, work declaration, and confirmation from the professional or relevant authority. When the deadline is tight, obtain a written position rather than relying on a verbal interpretation.

Building and Electricity: Two Chapters, Two Analyses

The same final date does not mean that the two chapters are interchangeable. The Building chapter specifically targets the construction and transformation of the building. The Electricity chapter governs the construction of the electrical installation. The effective dates of their new editions are different, and the work involved may also start at different times on the same project.

A general contractor should not assume that the choice made for the building automatically resolves the electricity. The electrical contractor, professionals, and the client must coordinate the edition used in the plans, specifications, calculations, power requests, and work.

The case of multi-dwelling units and charging stations

The new electrical requirements notably affect the basic infrastructure intended for powering stations in certain multi-dwelling units. The Government of Quebec indicates that for buildings with more than four units, this requirement will become mandatory on October 17, 2027, following the extension.

A multi-residential project in design should therefore immediately verify the reserved space, electrical capacity, cable paths, panels, and future costs. Using the old edition may be allowed during the transition, but completely ignoring future needs may shift the expense to the owner or co-owners after delivery.

Why the government extended the transition

When announcing the postponement, the Minister of Labour cited industry concerns about the impact of new requirements on construction costs. The government also indicated a desire to allow for broader consultation and tasked the Régie du bâtiment du Québec with reflecting on possible adjustments.

The extension aims to provide more predictability for projects already underway and time to examine certain requirements. It does not mean that the objectives of safety, accessibility, or building adaptation have disappeared. It creates an additional period where teams must make a documented choice.

Should the old edition be automatically chosen?

No. The least costly choice in the short term is not always the most advantageous over the building's lifecycle. A project delivered according to the old edition may have to deal sooner with market expectations, accessibility needs, charging infrastructure, or an owner's requirements that exceed the regulatory minimum.

Conversely, immediately adopting the new edition may require updating plans, details, and prices. The right decision depends on the project's progress, probable start date, building type, involved disciplines, budget, municipal requirements, and accepted risk level.

Avoid choosing article by article

The transitional period should not be interpreted as a general permission to take the least demanding elements from each edition. The team must clearly identify the regulatory basis used and verify cross-references between articles, standards, and disciplines. An uncoordinated mix can produce incompatibilities and make compliance difficult to demonstrate.

Municipalities and other rules still matter

The provincial Construction Code is not the only text applicable to a project. Zoning, permits, municipal regulations, fire protection, environment, energy efficiency, contractual requirements, and standards incorporated by reference can add other obligations.

A municipality may also require specific documents before issuing a permit or authorizing work. The provincial extension should not be presented as a general exemption. The team must verify the entire applicable framework for the building and project location.

A simple method to secure the project

Decision tree for choosing the Construction Code edition based on the work start date

1. Identify the chapters actually concerned

At a minimum, distinguish between building and electricity. Add other chapters, standards, and regulations that affect the project. Each discipline should confirm its design basis.

2. Set a realistic start date

Do not work only with the desired date. Consider the permit, financing, tenders, critical orders, season, authorizations, and labour availability.

3. Choose and record the edition in the documents

Plans, specifications, calculation notes, estimates, contracts, and addenda should name the edition used. This precision limits different interpretations between the professional, general contractor, and subcontractors.

4. Plan for a delay scenario

If the site is likely to start after October 17, 2027, evaluate the necessary modifications to comply with the new edition from the design phase. Identify who will assume the update of plans, additional materials, and delays.

5. Keep proof and verify on-site

Good work supervision and compliance traceability help link approved plans, the declared edition, and what is actually built. For sensitive elements, a quality execution inspection also allows for correcting discrepancies before they are hidden by subsequent work.

Three concrete examples

Project designed in 2026, site started in September 2027

If the targeted work actually begins before October 17, 2027, and the project is eligible for the transitional measure, the old edition can still be used. However, this choice must be documented, and the requirements of all disciplines must be verified.

Permit obtained in August 2027, construction started in November

The previous permit is not enough to automatically preserve the old edition. Since the work begins after the deadline, the project should be prepared according to the applicable new edition, subject to official confirmation specific to the case.

Building started before the deadline, electricity later

The start of the building should not be used without analysis as the sole date for the electrical installation. Electrical work has its own transitional chapter. The master electrician and professionals must confirm the applicable rule for the installation and retain relevant evidence.

Myths to Dispel

"The new Code is cancelled until 2027"

False. The new editions are already in effect. The period during which the old provisions can still be used has been extended.

"A permit before October 2027 guarantees the old Code"

False. The regulation ties the transition to the start of the work. The permit remains important, but its date does not automatically replace the regulatory criterion.

"You can choose the cheapest articles in each edition"

To be avoided. The provisions of an edition form a set with cross-references and interactions. The choice must be consistent and validated by the responsible stakeholders.

"All small works are concerned in the same way"

False. The applicability depends on the building, the nature of the work, the chapter concerned, and municipal or specific rules. A limited repair is not analyzed like new construction or a major transformation.

What Will Happen After October 17, 2027

For work that will begin after the end of the transitional period, previous editions can no longer be used solely based on this measure. The new provisions will then become the mandatory reference for the work subject to them.

Until then, the government and the RBQ can still publish clarifications or modify certain requirements. Projects that span several years should therefore maintain regulatory monitoring and verify the texts in force at the time of deciding, submitting, and starting the work.

Key Takeaways

The new official date is October 17, 2027. It extends the possibility of using the old provisions of the Building and Electricity chapters for work started before this date. It does not postpone the entry into force of the new codes.

The practical decision rests on four actions: confirm the applicable chapters, establish a credible start date, clearly record the chosen edition in the documents, and plan for what will happen if the construction is delayed. For a project close to the deadline, written confirmation from the competent authority or the responsible professional is worth much more than an assumption.

This article presents general information. The applicable edition must be validated according to the building, the nature of the work, the municipality, and the regulatory documents in force at the time of the project.